← Back to projects

Santa Monica

17th Street ADU project

1417 17th Street, CA 90404

Project overview

Existing units
6
Scope
Garage conversion
Construction start
December 2025
Reported phase
Drywall / taping / mudding
Project notes & sources

Drywall & interior work

Company record · 2026-06-17

The August 2026 completion date was a forecast. Current completion has not been independently verified.

Gallery: design studies and archive photographs; neither establishes current completion.

  • Published portfolio image · medium unverified
  • Published project gallery image · medium unverified
  • Published project gallery image · medium unverified
  • Published project gallery image · medium unverified
  • Published project gallery image · medium unverified
  • Published project gallery image · medium unverified
Original project source ↗

More projects

Claire wearing a Rolen hard hat

ROLEN CONSTRUCTION

Let’s talk.

(424) 275-2755

Monday–Friday · 9 am–5 pm
Pacific Time